After preparation you are required to confirm that your efforts so far meet council regulation prior to concreting. You will also need to check to your own satisfaction that issues such as drainage and termite protection have been given proper attention.

NB: If these plans etc are not on site when an inspection is called, the council inspector will not pass the job - and you will have to re-book another inspection. This will only cause delays on site.
Includes a site inspection by certifier and a footing / pier inspection by certifier or engineer. Site inspection and footing / pier inspection can be done at same time by the certifier.
Inspections will include checking for things such as :
WORK CAN NOT CONTINUE TO THE NEXT STAGE UNLESS A FORM 16 STAGE CERTIFICATE HAS BEEN ISSUED BY THE CERTIFIER.
Can be done by an engineer, but notification will need to be given to the certifier.
Inspections will include checking for things such as:
WORK CAN NOT CONTINUE TO THE NEXT STAGE UNLESS A FORM 16 STAGE CERTIFICATE HAS BEEN ISSUED BY THE CERTIFIER.